The Life-cycle cost (New Version) tool applies default material and labour costs from a reference cost database. This article explains the assumptions behind those default costs, so you can check whether they fit your project and decide when to replace them with your own figures.
How each default cost is defined
Each cost category is based on the same five elements:
Material classification: the typical product the cost is based on, including its specification, format, and indicative mass (per unit, per m, per m2, or per kg).
Pricing basis: the type of pricing the material cost reflects and which products are left out.
Labour basis: the installation assumptions, such as crew size, output rates, or labour-hours per unit, and the site conditions assumed.
Includes: what the default cost covers.
Excludes: what is not in the default cost and needs to be added separately if it is in your scope.
Assumptions behind the default costs
Most cost categories share these assumptions:
Indicative ranges, not quotes. Default costs are budget-level figures for comparing options at early design stages. They are not tender prices or supplier quotations.
Standard, mainstream products. Pricing reflects standard, construction-grade products from mainstream ranges. Premium brands, designer ranges, bespoke specifications, and specialist variants are excluded.
Normal wastage. Most categories allow for normal cutting and wastage on straightforward work.
Normal site conditions. Labour assumes clear and safe access, workable site conditions, and routine handling equipment.
What is usually excluded
Default costs usually exclude the items below.
Preliminaries (site set-up and management costs), overheads, and profit
VAT and other taxes
Access equipment, temporary works, and protection
Abnormal access arrangements or specialist lifting
Design work
Testing, commissioning, and documentation beyond supplier data
Example: Ready-mix concrete
Material classification: normal-weight ready-mix concrete, strength class C30/37, with 20 mm aggregate, for general structural use.
Pricing basis: a standard mix delivered by truck mixer, with a standard plasticiser only. Special mixes, fibres, small-load charges, and out-of-hours delivery are excluded.
Labour basis: a team of three to four people placing 10 to 20 m3 per day in straightforward slabs or strip footings, with clear access and a continuous supply.
Includes: concrete supply, placing to line and level, compaction with a vibrator, and basic levelling.
Excludes: formwork, reinforcement, pump hire, power floating or fine finishing, curing, joints, and strength testing.
If your concrete rate includes pumping, formwork, or finishing, it will be higher than the default cost. This does not mean either figure is wrong.
Examples: Common construction materials
The table below summarises the default cost assumptions for fifteen of the most common construction materials. For other specific assumption details, please contact our Support.
Material | Based on | Pricing | Installation | Key exclusions |
Ready-mix concrete (C30/37) | Normal-weight C30/37 concrete with 20 mm aggregate, for general structural use | Standard mix delivered by truck mixer, with a standard plasticiser only | A team of three to four people placing 10–20 m3 per day | Formwork, reinforcement, pump hire, finishing, curing, and testing |
Reinforcing steel bars | B500C ribbed bars, 10–32 mm, cut and bent to schedule | Supplied cut and bent, and delivered to site | A team of two fixing 30–50 kg per labour-hour | Couplers, spacers and chairs, prefabricated cages, and cranage |
Structural steel sections | S275/S355 hot-rolled beams and columns, unpainted | Standard sections delivered to site, with no fabrication | Lifting into place and bolting to prepared connections | Fabrication, paint and fire protection, cranage, holding-down bolts, and decking |
Structural softwood | Kiln-dried C16/C24 timber, planed and strength-graded | Standard supply, with 3–5% allowance for off-cuts | 4–8 labour-hours per m3 for general carpentry | Preservative and fire-retardant treatments, finishes, and engineered connectors |
Cross-laminated timber (CLT) | Standard spruce CLT panels, structural grade | Supplier rates, with no coatings or surface treatments | Placing and fixing pre-cut panels with screws and plates | Cranage, shop drawings, coatings, and fire or acoustic treatments |
Portland cement (CEM I) | Grey, general-purpose CEM I to EN 197-1 | Bulk or 25 kg bags, with 1–2% allowance for spillage | Handling only, as mixing and placing are priced in concrete and mortar | Aggregates, admixtures, mixing equipment, and delivery surcharges |
Crushed stone sub-base | Type 1 crushed rock, 20–63 mm | Full-load deliveries | Spreading and compacting by machine in 100–250 mm layers | Geotextiles, testing, extra excavation, and traffic management |
Clay bricks | Common and engineering clay bricks, about 2.3 kg each | Standard bricks, with normal breakage | Standard bricklaying with straightforward coursing | Mortar, wall ties, lintels, scaffolding, and special bricks |
Concrete blocks | A mix of hollow, medium-density, and dense blocks with a plain finish | Standard blocks, with normal cutting waste | A bricklayer and an assistant, including general-purpose mortar | Reinforcement and grout, lintels, damp-proof courses, finishes, and scaffolding |
Plasterboard | 12.5 mm standard plasterboard (EN 520 Type A) for walls and ceilings | Standard boards, with no fire-, moisture-, or sound-rated grades | 0.20–0.35 labour-hours per m2, fixing only | Taping and jointing, trims, rated boards, and extra framing |
Stone wool insulation batts | Unfaced stone wool batts fitted between studs or in cavities | Standard batts, with no high-density products | 0.12–0.16 labour-hours per m2 | Tapes, vapour control layers, airtightness details, and access equipment |
EPS insulation boards | Unfaced rigid EPS boards to EN 13163 | Standard boards with standard adhesive | One to two people fixing 30–60 m2 per day | Render and mesh for external wall insulation systems, fire barriers, trims, and surface preparation |
Insulating glass units | Double-glazed units, clear low-E glass, 24–28 mm thick | Factory-sealed units, with no special glazing | Fitting into prepared frames | Frames, solar-control or acoustic glazing, and access arrangements |
Aluminium | Sheet and extrusions, mill or standard anodised finish | Standard grades | Light fabrication and fixing, 0.05–0.12 labour-hours per kg | Façade systems, premium finishes, and access equipment |
Hot-mix asphalt | Base, binder, and surface course mixes | Asphalt plant rates for standard mixes | Laid by paving machine and rolled | Planing, tack coats, joints, traffic management, and testing |
Compare the default cost with your own figures
If a default cost differs from a quote or cost plan you have, check these points in order:
Specification. Compare your product with the Material classification. A different size, grade, or format is the most common reason for a difference.
Product range. Check the Pricing basis. Premium, designer, or specialist products cost more than the default.
Scope. Check whether your figure includes anything in the Excludes section, such as overheads, profit, or testing.
Site conditions. Restricted access, occupied buildings, or unusual handling increase labour time beyond the Labour basis.
Location. Check the project location and the Regionalised Cost Index in your LCC parameters.
Use your own cost data
Where you have project-specific prices, you can overwrite the unit cost or enter a total cost for a material. You can also adjust the Regionalised Cost Index to reflect local pricing. For step-by-step instructions, see Automated Life-Cycle Cost (New Version).
Frequently asked questions
Why does a category show no cost?
Some categories do not show pricing. For example, civil explosives are not priced for safety, regulatory, and market-sensitivity reasons. Contact manufacturers or licensed distributors for a quotation and enter the cost manually.
Are labour costs always included?
Labour is included when "Include Labour Costs" is turned on in your LCC parameters. The "Labour basis" section describes the installation work that the labour cost covers.
Can I use default costs for a tender or final cost plan?
Default costs are indicative and suited to early-stage comparisons. For tenders and final cost plans, use project-specific prices from your cost consultant or suppliers.